As
of BW
7.0 we need to manually change all the delta init
packages in the process chains to delta when we move the changes to QA or
Production environments or we have to create separate delta init packages and
manually run them to do initialization before we could schedule the process
chains with delta info packages. This is going to change in SAP
BW 7.3.
There is a new option
"Switch Info Package. In PC to Delta" under update tab of info package.
If we check this option the info package will be automatically executed as delta
package if already there is a successful initialization. Otherwise, it will be
executed as ainit package when there is no successful initialization. This will
be useful and save us some time with new projects and
enhancements.
Screenshot of "Switch Infopackage.in PC to Delta"
option
F1 Help for 'Switch Infopackage. in PC to
Delta"
Convert
Initial Info Package into Delta Info Package
You use this
indicator to specify whether you want the system to automatically convert an
Info Package that is being used in a process chain into a delta Info Package
when the delta transfer has been initialized
successfully.
Use
If you set
this indicator, the following applies to the Info Package when it is executed in
a process chain.
If you set the Initialization of Delta
Process indicator on the Update tab page and there is no active initialization
request with the same or overlapping selections for this Data Source/source
system combination,the Info Package is executed as an initialization Info
Package.
If there are one or more active initialization
requests with the same or overlapping selections for this Data Source/source
system combination, the InfoPackage is converted to a delta InfoPackage just
before it is executed in the process chain. After it has been converted, the
Info Package stays as a delta Info Package
in the process chain.
in the process chain.